Partner Construction wins appeal against Durham
The county council’s objections to the impact the 156 homes would have on the landscape in Coundon were not enough to win over the Planning Inspectorate, which ruled that a lack of a five-year housing land supply overrode those concerns.
Partner Construction had its outline application for 156 homes refused in March after having received robust community backlash. It was the second time Partner Construction’s plans for the site had been rejected, with a previous full planning application refused by Durham County Council in September 2025.
The 26-acre site in question sits west of Westerton Road and has been used as farmland. As a note, recent soil tests showed that it was not Best and Most Versatile agricultural land.
The outline application included indicative layouts that showed how there could be more than 10% biodiversity net gain under the proposals as well as adequate public space, according to the planning inspector. Under the plans drawn up by Partner Construction, approximately 50% of the site would be open space.
Chief among the elements weighing in favour of the application was the council’s 3.92-year housing land supply, which is short of the five-year required by government.
Lichfields led the planning submission for Partner Construction. The project team also includes Ergo, FPCR, RWO, Lanpro, Archaeological Services Durham University, ITransport Planning, Shadbolt, Miller Goodall, and Wardell Armstrong.
To learn more about the application search reference DM/25/03489/OUT on Durham County Council’s planning portal, or reference 6009574 on the Planning Inspectorate’s site.